Continuation of supervision of construction work on the ''Electricity Distribution'' project, transferred to the Beninese Electricity Company (SBEE) by MCA-Benin II. |
The MCA-Benin II Project was completed by the closing date of the Compact on 22 June 2023, with the exception of the contract for the IPP connections of the EIFFAGE/RMT Contractor. The post-completion supervision activity focuses on the removal of reservations and the correction of defects during the Defect Notification Period, in collaboration with the SBEE teams. The current assignment is aimed at supervising the construction work on the connections for the four IPP solar power plants, as well as the removal of reservations for the other contracts, in accordance with standards and contractual requirements. |
| |